Báo cáo tháng và đánh giá tiến độ của nhà thầu tiếng anh
Hanoi- HaiPhong Expressway Project
VIETNAM INFRASTRUCTURE DEVELOPMENT
AND FINANCE INVESTMENT JOINT STOCK COMPANY
CONSTRUCTION SUPERVISION OF
HANOI – HAI PHONG EXPRESSWAY PROJECT
PACKAGE EX2
MONTHLY REPORT & ASSESSMENT OF
CONTRACTOR’S PROGRESS REPORT
MARCH 2014
CONSULTANT
MEINHARDT INTERNATIONAL – VJEC
JOINT OPERATION
Monthly Progress Report No.48, February 2014
Package EX2
Hanoi- HaiPhong Expressway Project
PACKAGE & CONTRACT INFORMATION
General Information
Package Location
Chainage
Package Length
Employer’s Representatives
Engineer
Contractor
Hung Yen Province
Km 6+200 – Km19+000
12.8 Km
Hanoi–Haiphong Expressway Project Management
Board (PMB)
Meinhardt VJEC Joint Operation (MI-VJEC)
Namkwang Engineering& Construction Co.,LTD)
Contract Dates
Date of Approval Letter
Date of Contract Agreement
Date of Notice to Proceed
Original Time for Completion
Mobilization Period
Time for Completion after Mobilization
Original Date for Completion
5th April 2010
6th April 2010
10th June 2010
1095 days (36 months)
45 days
1050 days
9th June 2013
Extension of Time for Completion
Approved Extension of Time for Completion
Extended Date for Completion
Approved Extension of Time for Completion
according to the EOT signed off between the
Employer and the Contractor on 18 Mar 2014
Extended Date for Completion
6 months (183 days)
10 December 2013
690 days from 10/06/2013
30/04/2015
Orginal Contract Value
Original Gross Contract Price
VND 1.820.561.000.000
((Net Contract + VAT) + 5% Contingency and 20% Price Adjustment))
Original Net Contract Price
VND 1,324,044,081,575
=USD 71,662,918.47
Based on Fixed Exchange Rate
18.476 (for conversion of Foreign Currency Portion
into VND)
Local Currency Portion
VND 413.000.648.689
Original Foreign Currency Ratio
USD 31, 19%. VND 68, 81%
Additional Information: Appendix to the Conditions of Contract
Amount of Performance Security
: 10% of the Contract Amount
Amount of Liquidated Damages
: 0.1% of the Contract Amount per one day delayed
Limit of Liquidated Damages
: 12% of the Contract Amount
Defects Liability Period
: 36 months
Minimum Amount of IPC
: VND 7,000,000,000
Retention Money
: 10% of Interim Payment Certificates amount from
IPC 01 to IPC 28; 5% from IPC 29 to IPC 31
Cut-off date for this report
: 20 Mar 2014
Updated Interim Contract Value (based on Approved Shop Drawing Quantities)
Updated Interim Contract Net Value on 15/11/2013: VND 1,168,081,048,904
= USD 63,221,533.28
Construction Schedule
Latest Programme
: Revised Construction Schedule, Revision 5
Monthly Progress Report No.48, February 2014
2
Package EX2
Hanoi- HaiPhong Expressway Project
Date for Completion as Revised
Construction Schedule, Revision 5
Amount for Liquidated Damages
:
: 30 April 2015
: 0.1% of the Contract Amount per one day delayed
Progress against Schedule
Time for Mobilization:
No later than 45 days after the date of Notice
to Proceed
Execution time:
1.740 days
% of Elasped time
1.367 / 1.740 = 79.08% (elapsed time)
Progress against Schedule (Value):
+100.00% (As Approved Clause 14.1
Programme)
+51.25% (As Revised Construction Schedule,
Revision 05)
Actual Overall Progress (Value):
51.45 %
Actual slippage compared with Clause 14.1 Programme: -48.75%
Actual slippage compared with Construction
Schedule Rev.5:
+0.2%
Monthly Progress Report No.48, February 2014
3
Package EX2
Hanoi- HaiPhong Expressway Project
1. Construction Progress
1.1 Cummulative construction progress from the commencement date up to 20 Mar 2014
Package
EX2
Completed
Million VNĐ
Planned
%
600,985
Million VNĐ
51.45
Slippage
(+ / -)
%
598,649
51.25
+0.20
Note: % progress achieved is a division of Completed value by the estimated adjusted Net
contract value (excluding VAT, contingency and price adjustment – Column 6, Table 1.5)
1.2 Construction progress in Mar 2014
Package
Completed
Planned
Million VNĐ
EX2
%
23,674
Million VNĐ
2.03
20,896
%
Slippage
(+ / -)
1.79
+0.24
Note: % progress achieved is a division of Completed value by the estimated adjusted Net
contract value (excluding VAT, contingency and price adjustment – Column 6, Table 1.5)
1.3 Summary of cumulative disbursement from the commencement date to 20 Mar 2014
Package
EX2
Disbursement
Million VNĐ
%
779,937
Planned Disbursement
Million VNĐ
%
42.84
876,782
Difference (+ / -)
Million VNĐ
%
48.16
-96,845
-5.32
Note: % disbursement rate is a division of total monthly IPC value (including IPC value +
advanced value) by the Contract value (including VAT, contingency and price adjustment).
-
Monthly IPC value was approved by the Engineer.
1.4 Summary of disbursement in Mar 2014
Package
EX2
Disbursed
Million VNĐ
%
Disbursement plan
Million VNĐ
%
36,755
34,598
2.02
Difference (+ / -)
Million VNĐ
%
1.90
2,157
0,12
Note:
-
% disbursement rate is a division of total monthly IPC value by the Contract value
(including VAT, contingency and price adjustment).
-
Monthly IPC value has been approved by the Engineer.
1.5 Estimated adjusted contract value (excluding VAT, contingency and price adjustment)
Unit:1.000.000 dong
Net Contract
Net Original
value (original
Contract
Package
contract) +
value +
Addendum
Addendum
(adjusted)
(1)
(2)
(3)
EX2
1,324,044
953,777
VOs’ value
Estimated adjusted
contract value
Approved
Not-yetapproved
(4)
(5)
(6)=(3)+(4)+(5)
6,041
209,312
1,168,081
1.6 Value of approved VOs (excluding VAT and contingency)
Monthly Progress Report No.48, February 2014
4
Package EX2
Hanoi- HaiPhong Expressway Project
Unit:1.000.000 dong
VO No.
VO#1
VO#2
VO#3
VO#9
Tổng
Content
Construction of service road at Hoa Muc village
Construction of service road at Toll Plaza
Additional geotechnical investigation
Increase in quantities of PVD&SCP
Value
Note
718
4,245
370
708
6041
Already approved
Already approved
Already approved
Already paid
1.7 Value of not-yet-approved VOs (excluding VAT and contingency)
Unit:1.000.000 dong
VO No.
Content
VO#4
Change B35’s structure
VO#11
Underpass in replacement of
B39’s Bridge
Total
Note:
Estimated
value
Note
206,924
The Engineer issued a letter
to request the Contractor to
supplement on 05 Mar 2014
and issued a letter to the
H.O on 05 Mar 2014.
2,208
209,312
Reasons of arising VO:
- Update of quantity in the Shop drawings and arising quantity
- Reduction of quantity due to quantity reduction as instructed by Ministry of
Tranportation
- Increase/Decrease of quantity due to some other reasons
Monthly Progress Report No.48, February 2014
5
Package EX2
Hanoi- HaiPhong Expressway Project
1.8. S-Curve (Equivalent to Construction Schedule Revision 5)
Monthly Progress Report No.48, February 2014
6
Package EX2
Hanoi- HaiPhong Expressway Project
1.9 MOT Required Information
1.9.1 Cummulative progress from the commencement date to 20 Mar 2014
Hạng mục chính
Đơn vị
(1)
EFS removal
Construction of Subgrade
(30cm Layer)
Construction of
Embankment K95 (below
Subgrade)
Construction of Cohesive
Slope
Embankment for Settlement
(2)
m3
Khối lượng
Hoàn thành
(4)
Hợp đồng
(3)
Chênh lệch
(+ / -)
Kế hoạch
(5)
(6)
300,105
158,782
121,844.60
36,937.22
m3
129,204
59,855
61,242
-1,387
m3
1,384,226
1,317,215
1,311,360
5,854.7
m3
197,984
157,169
154,762
2,407
m3
314,185
Granular backfill (K95)
m3
20,752
Aggregate base course
Pre-fabricated Vertical Drain
(P.V.D)
Vertical Sand Drain,
diameter 0.4m (S.D)
m3
193,179
237,246
19,033
20,580
237,246
17,535
26,656
1,498
-6,077
lm
202,364
202,364
202,364
lm
208,620
208,620
208,620
Coarse Sand Blanket
m3
147,869
145,791
145,791
lm
41,879
41,879
41,879
m3
30,605
30,605
30,605
lm
679
236
236
lm
2,110
1,289
1,336
m3
999
999
999
m3
2,307
269
107
162
m3
1,891
693
518
175.44
m3
9,529
5,807
6,815
-1,008.52
m3
1,820
1,820
1,820
m3
3,165
457
426
m3
8,598
8,241
8,241
Sand Compaction Pile,
diameter
Surcharge
Reinforced Concrete Pipe
Culvert, Type CP-1250
Reinforced Concrete Pipe
Culvert, Type CP-1500
Cast-in-situ Prestressed
Concrete for Pier Head Class B- 40MPa
Concrete for deck slab –
Class D
Concrete for deck slab and
diaphragm Class D-30Mpa
Cast-in-situ Concrete for
Abutments and Piers - Class
D
Cast-in-situ Concrete for
Abutments and Piers - Class
D (B35)
Cast-in-situ Concrete for
Approach Slab and
structures of Box Culverts Class E
Bored pile - 1,200mm
diameter
Monthly Progress Report No.48, February 2014
8
-46.75
31.28
Package EX2
Hanoi- HaiPhong Expressway Project
Bored pile - 1,200mm
diameter
Prestressing cable - Type
15.2mm for the pier head
PC-I Girder; Length 25 m
(B18) precast
PC-I Girder; Length 25 m
(B18) launching
PC-I Girder; Length 25 m
(B35) precast
PC-I Girder; Length 25 m
(B35) launching
PC-I Girder; Length 33 m
(B35) precast
PC-I Girder; Length 33 m
(B35) launching
Super T Girder; Length
38.3m precast
Super T Girder; Length
38.3m launching
Round deformed bar
Steel bearing, type
350x500x78
Elastomeric bearing, type
300x550x78
lm
6,612
6,556
6,558
-2
kg
26,640
17,787
18,893
-1,107
14
5
each
5
each
14
14
73
73
42
42
36
53
-17
20
25
-5
2,811,338
1,927,839
1,516,266
411,573
each
168
73
73
each
170
40
50
-10
-2
each
each
84
each
each
99
each
each
kg
Drainage box culvert
(1500x1500)
lm
1,097
449
451
Drainage box culvert
(2000x2000)
lm
433
88
88
Drainage box culvert
(3000x2000)
lm
242
105
105
Drainage box culvert
(3000x3000)
lm
416
86
103
Underpass (6500x3200)
lm
49
49
49
Underpass (4000x2700)
lm
485
358
357
-18
1.00
1.9.2 Construction progress in Mar 2014
Hạng mục chính
(1)
Removal of Embankment
for Settlement
Construction of Subgrade
(30cm Layer)
Đơn vị
(2)
Chênh
lệch
(+ / -)
(6)
Khối lượng
Hợp đồng
Hoàn thành
Kế hoạch
(3)
(4)
(5)
m3
300105
18493.76
3429
15064.76
m3
129,204
8,517
8,577
-60.15
Monthly Progress Report No.48, February 2014
9
Package EX2
Hanoi- HaiPhong Expressway Project
Construction of
Embankment K95 (below
Subgrade)
Construction of Cohesive
Slope
Embankment for Settlement
m3
1,384,226
12,298
7,633
4,665
m3
197,984
2,175
2,648
-472
m3
314,185
-
-
m3
20,752
-
-
Aggregate base course
m3
Pre-fabricated Vertical Drain
lm
(P.V.D)
Vertical Sand Drain,
lm
diameter 0.4m (S.D)
193,179
10,882
13,229
202,364
-
-
208,620
-
-
Coarse Sand Blanket
m3
147,869
-
-
lm
41,879
-
-
m3
30,605
-
-
lm
679
-
-
lm
2,110
-
76
m3
999
-
-
2,307
269
107
162
1,891
12
4
-
124
9,529
36
5
919
-554
-
-
-
-
-
-
53
8
270
268
-
1,107
-1,107
-
5
Granular backfill (K95)
Sand Compaction Pile,
diameter
Surcharge
Reinforced Concrete Pipe
Culvert, Type CP-1250
Reinforced Concrete Pipe
Culvert, Type CP-1500
Cast-in-situ Prestressed
Concrete for Pier Head Class B- 40MPa
Concrete for deck slabbb –
Class D
Concrete for deck slab and
diaphragm Class D-30Mpa
Cast-in-situ Concrete for
Abutments and Piers - Class
D
Cast-in-situ Concrete for
Abutments and Piers - Class
D (B35)
Cast-in-situ Concrete for
Approach Slab and
structures of Box Culverts Class E
Cast-in-place concrete pile 1,200mm diameter
Cast-in-place concrete pile 1,200mm diameter
Prestressing cable - Type
15.2mm for the pier head
PC-I Girder; Length 25 m
(B18) precast
PC-I Girder; Length 25 m
(B18) launching
PC-I Girder; Length 25 m
m3
m3
m3
m3
m3
m3
lm
kg
each
1,820
3,165
8,598
6,612
26,640
14
5
each
-
-
each
-
-
Monthly Progress Report No.48, February 2014
10
-2,347
-76
Package EX2
Hanoi- HaiPhong Expressway Project
(B35) precast
PC-I Girder; Length 25 m
(B35) launching
PC-I Girder; Length 33 m
(B35) precast
PC-I Girder; Length 33 m
(B35) launching
Super T Girder; Length
38.3m precast
Super T Girder; Length
38.3m launching
-
-
84
5.
0
4.0
1
-
7
99
7
9.
0
17.0
-8
each
each
each
each
-
-
2,811,338
64,76
4
68,680
-3,916
168
3
6
-3
each
Round deformed bar
kg
Steel bearing, type
350x500x78
each
Elastomeric bearing, type
300x550x78
each
Drainage box culvert,
(1500x1500)
lm
Drainage box culvert,
(2000x2000)
lm
Drainage box culvert,
(3000x2000)
lm
Drainage box culvert,
(3000x3000)
lm
Underpass, (6500x3200)
lm
Underpass, (4000x2700)
lm
170
1,097
433
242
416
49
485
-
-
-
-
-
-
-
-
-
-
-
-
-
-
1.9.3 Mobilization of major equipment
List of equipment/
machine
Required
quantity
(1)
Excavator
Bulldozer
Motor grader
Vibrating
Tyred roller
Steel Wheel roller
Wheel loader
SD & SCP machine
PVD machine
Bored pile machine
Crane
(2)
7
5
2
14
1
2
2
0
0
1
4
Monthly Progress Report No.48, February 2014
Quantity of
equipment/ machine
mobilized to the site
(3)
9
5
3
14
1
0
2
0
0
1
5
11
Difference
Remarks
(4)
2
0
1
0
0
-2
0
0
0
0
1
(5)
Package EX2
Hanoi- HaiPhong Expressway Project
Concrete pump
Concrete batching plant
Concrete truck
Water truck
Aggregate paver
Asphalt paver
Asphalt mixing plant
0
2
3
2
1
0
0
0
2
3
2
1
0
0
0
0
0
0
0
0
0
Required
quantity
Quantity of
personnel mobilized
Difference
Remarks
(2)
1
1
1
1
(3)
1
1
1
1
(4)
0
0
0
0
(5)
1
1
0
1
1
0
1
1
0
1
1
1
1
0
0
1
1
0
1.9.4 Mobilization of key personnel
List of key personnel
(1)
Project Manager
QC Manager
Substructure Engineer
Superstructure Engineer
Geotechnical/SST Engineer
Embankment/Pavement
Engineer
Quantity & Payment
Engineer
Material Engineer
Chief of Laboratory
Environmental Control
Manager
2. Construction quality
The Contractor has done his own quality control in compliance with the approved Quality Control
Plan.
The Contractor has sufficiently arranged his own engineers for quality management during the
construction and given technical guidance on the trial construction prior to any mass construction.
The Contractor has arranged the site laboratory in collaboration with the external laboratory to
check and test materials and work structures timely.
The Contractor fulfills his responsibilities of Works quality, assuring that all materials and Works
items are correctly incorporated into the Works and built in accordance with the Design and
Specification.
3. Difficulties of the Package
The previous lack of finance has since been solved with the payment of the Additional Advance
Payment of 79 billion, and we therefore expect more improvement than has been demonsstrated.
However the Tet holiday has resulted in a slow start-up especially with the VNC Contractor for
Base Course.
Lack of initiative to now improve progress with extra shifts with more work fronts and with
replacement of Subcontractors eg. the subcontractor to replace Thai Duong.
VOs and IPCs have not been solved thoroughly and quickly enough.
Monthly Progress Report No.48, February 2014
12
Package EX2
Hanoi- HaiPhong Expressway Project
4. Proposed Solutions
Enhance equipment and teams and work fronts to catch up the slippage in the construction of
subgrade and base and bridge work and also to enhance the acceptance documents and payment
procedures.
5. Report of Package EX2 Engineer Site Office
5.1 Highway Engineer Monthly Report
5.1.1 Construction Progress of Embankment – Linear Metres
Package
Total
(m)
5.196
EX 2
Stage 1
Actual
(m)
5196
Stage 2
Actual
(m)
741
Total
(m)
741
%
100
Stage3
Total Actua
(m)
l (m)
0
%
100
%
EFS removal
Total
Actual
(m)
(m)
5.196
3896
%
75
5.1.2 Construction Progress of Base aggregate
Package
Total
(m)
12470
EX 2
Layer 1
Actual
(m)
922
Layer 2
Actual
(m)
1576
Total
(m)
12470
%
7.4
Layer 3
%
Total (m)
Actual (m)
%
12.6
12470
1976
15.85
5.1.3 Construction Progress of Pavement layers
Package
EX2
Total (m)
Actual (m)
%
11.710
0
0%
Total (m)
Actual (m)
%
Total (m)
Actual (m)
%
5.1.4 Reasons for the progress delay and mitigation methods
Package
Section
Layer
Reason
Note
reference
Mitigation
and
Supplement the table “Status of Embankment Construction” (soft-copy)
Supplement “Status of culvert construction” (soft-copy)
5.2 Geotechnical Engineer’s Monthly Report
5.2.1 Soft Soil Treatment Progress – Completed Quantities
EX2
Total
(m)
PVD
Complete
(m)
202,364
202,364
%
Complete
(m)
SD
Actual
(m)
100
%
208,620
208,620
Monthly Progress Report No.48, February 2014
%
13
100
%
SCP
Complete
Actual
(m)
(m)
41,879
41,879
%
Comment
100
%
Package EX2
Hanoi- HaiPhong Expressway Project
5.2.2 Reasons for the progress delay and mitigation methods
Package
Section
Type
SST
pf
Reason
Mitigation
Note and reference
EX2
5.3.
Topographical Engineer’s Monthly Report
5.3.1. SUMMARY TABLE OF ISSUES CONCERNING THE LAND ACQUISITION ON
PACKAGE EX2
I
1
2
3
4
5
Item
Main road, Interchange
Main road
Frontage road
Interchanges
Flyover
Access roads
6
Main road sections
7
8
9
10
II
1
2
3
4
5
6
Toll plaza
Parking area
Culverts
Channel Relocations
Utilities
Communication Cable
Electric Cable
Electrical Substation
Electric Pole
Water line
Others
FROM KM6+200 TO KM19+00
Total
Handed over
Outstanding
Ratio
12,8km
12,8km
0
100%
3
3,09km
66
sections
1 km
-
3
3,09km
0
0
100%
100%
66 sections
0
100%
1 km
-
0
-
100%
-
Remark
5.3.2 Survey and Management of Control Network System on the Package (including GPS Class
IV, secondary control network – technical level, construction control network & embankment
settlement monitoring points)
Package
Status
EX- 2
Conducted Periodical check: 6th time
Actions by Engineer
Date 18 Month 06 Reference Letters
Year 2013
23 - 1 - 2014
EX2/C/03.2/L2475
5.4. Materials Engineer’s Monthly Report
Material Quality Control
5.4.1 Laboratories
No
Package
Site laboratories
Location
Operation status
Monthly Progress Report No.48, February 2014
External independent laboratories
Location
Operation status
14
Package EX2
Hanoi- HaiPhong Expressway Project
1
EX2
Mentioned in details in letter Ref
ITST;
Km17+740 IL-HO/RP/0557
issued
on
HàNội
30/1/2013
IBST; Satisfactory
Project
requirements
5.4.2 Sources of Materials
No
Package
1
EX2
5.4.3
Description of material sources
Sand
Embank
Sand for
Cohesive
Base
for SD
ment
CSB
soil
Aggregate
& SCP
sand
Lô
T10 RockRed
CủaRừng;
River,
Red River;
pit,
Đầu
River;
ThanhLiêm
Phú
HàNội
Mò;
Hà
HàNội
; Hà Nam
Thọ
Nam
EX2
2
3
4
EX2
EX2
EX2
5.4.4
2
Lô River
Phú thọ
Proposed solutions
No problem
Main Activities during January 2014
No
1
Concrete
course
sand
Problems of Material Quality on Site
No. Package Problems of material quality
1
Concrete
course
aggregate
T10 Rockpit, Đầu
Bò;
Hà
Nam
Main Activities on Site
To take samples and conduct the frequency tests of all materials in accordance with the Project’s
specification
To take sample for frequency of base and subgrade materials at the stockpiles and at the
construction lane as per the regulations of Package EX2
3
To take sample of black sand and cohesive soil at the EFS removal areas
4
To take sample for frequency of cement, Sika admixture, coarse aggregate, fine aggregate at the
cement-concrete batching plant (Km 17+500).
5
To take sample for anchorage and pre-stressed cable tests at B35 and B18 Bridges
6
To take sample of steel at the batching plant, bridges B35, B38 and B19
5.5 Bridge Engineer’s Monthly Progress Report
5.5.1 Summary of Bridge Construction Problems/ Anomalies
Package
EX2
Problem Description
- No
5.5.2
Contractors’ proposals
Remedial status
Note
- No
- No
-
Summary Table of Completed Quantity of Bridge work to Date
Items
Bored pile
EX2
D1.2m
(pile)
Design
Completed
Monthly Progress Report No.48, February 2014
308
300
15
Package EX2
to
Hanoi- HaiPhong Expressway Project
Sub-structure
(Pier, Abutment)
Girder
Bridge deck slab
(span)
Guard-rail bracket
(span)
Bridge deck asphalt
(span)
6.
%
Design
D1.5m
Completed
(pile)
%
Design
D2.0m
Completed
(pile)
%
Design
Completed
%
Design
PC-I
Completed
(girder)
%
Design
Super-T
Completed
(girder)
%
Hollow slab, Box Design
girder
Completed
(span)
%
Cantilever
box Design
girder
Completed
(m3)
%
Design
Completed
97.30%
%
Design
Completed
%
Design
Completed
%
23.08%
26
0
0%
26
0
0%
32
25
78.12%
112
91
81.25%
99
36
36.36%
26
6
Resident Engineer’s Assessment on Contractor’s Monthly Report for:
6.1 Progress against Monthly Plan
March had a planned progress of 2.03% but an actual progress of 1.79% resulting in an excess of 0.24%.
Monthly Progress Report No.48, February 2014
16
Package EX2
Hanoi- HaiPhong Expressway Project
6.2 Progress against the Plan- Clause 14
6.2.1 Activities on critical path
No.
1
Activitie
s
Km8+(220
-480)
Start date
Finish date
Schedule
Actual
Plan to
remove EFS
in March
Waiting for
decision to
remove EFS
10 Feb 2014
with A1
02 Mar 2014
with A2
Schedule
Actual
Delay
ed
days
Reasons
for delay
Delay
40 days
with
A2 and
18 days
with
A2
2
Soft soil
treatment
at A1, A2 B37
3
Breaking
pile head
at A1, A2 B18
24/1/2014
Not yet
construction
10/3/2014
Not yet
construction
55
Delay in
execution
4
Breaking
pile head
at A1-B19
23/1/2014
Not yet
construction
19/2/2014
Not yet
construction
56
Delay in
execution
Not yet
construction
Mitigations
To mobilize
equipment/pla
nt
To mobilize
manpower and
equipment,
speed up
construction
To mobilize
manpower and
equipment,
speed up
construction
6.2.2 Work activities are possible under risk to become critical activities
Start date
No.
1
Activitie
s
Breaking
pile heat at
A2 -B35
Sched
ule
2/3/2014
Finish date
Actual
Schedu
le
Actual
Not yet
construc
tion
21/3/201
4
Not yet
construct
ion
Delay
ed
days
The date that
work item
becomes a
critical
activity
18
3/2014
Reasons
for delay
Delay in
execution
Mitigatio
ns
Speed up
construction
Main items contributing to the March’s Slippage:
-
Construction of SuperT girder: As planned, the Contractor should have completed completed 39
Super T girders; but until now the Contractor has only completed 36 girders.
-
Construction progress of Base: According to the plan up to 20/03/2014, the Contractor should have
completed 26,656m3 but actually he achieved 20,580m3 only.
However, due to payment in advance of the base and steel materials, percentage of the packgage’s
progress exceeds the set plan.
-
6.3 Key Issues and Risks to Progress
Embankment section:
- Lack of equipment for embankment construction (roller) in order to make catch-up of the slippage in
Base and also Subgrade.
6.4 Contractor’s Resources Assessed Against Planned Work & Equipment Productivity
- Lack of equipment for the construction of embankment.
Monthly Progress Report No.48, February 2014
17
Package EX2
Hanoi- HaiPhong Expressway Project
- The Contractor should arrange work fronts for the construction of subgrade to ensure that the
progress shall not be delayed.
6.5 Contractor’s Plan for Next Month Assessed Against Conformance with the Construction
Schedule, Revision 05
The Contractor’s plan for next month has been reviewed and the Contractor is required to
revise and adjust in compliance with the Construction Schedule , rev.5
6.6 Assessments of Obstructions, Utilities, Delays and Compensation Issues
- No issue
-
6.7 Assessment of Contractor’s Design Issues
-
No issue
6.8 Assessment of Contractor’s Quality Issues and Quality Improvement Measures Adopted to
Mitigate
-
All NCR issues are being duly addressed.
6.9 Health, Safety and Environmental Issues. Assessment of Contractor’s Performance.
-
-
-
6.10
-
The workers and the engineers of the Contractor working at height have not yet fully and
strictly complied with wearing protective hat, safety belts and protective nets and this situation
worries the Engineer in terms of labor safety and environmental hygiene even though these
matters have been repeatedly reminded to Namkwang by the Engieer and even the Employer.
The Contractor should enhance traffic assurance at the intersections with provincial roads and
residential roads (to advoid such the accident happened on 25 Marr 2014 at the intersection of
B38 and PR206).
A second health and safety report has just been carried out by the H.O Specialist Mr.Walter
and very critical of the Contractor who has not instigated improvements in many health and
safety issues. A meeting will soon be programmed to focus on improvements.
Assessment of Contractor’s Financial Issues.
The Contractor should expedite the process of acceptance documentation for IPC since the
completed quantity is significantly more than the paid quantity, which negatively affects the
Contractor’s financial status.
The VOs has been slowly processed and handled by the Contractor, which affects the
disbursement process. Up to now, VO.01, VO.02, VO.03 and VO.09 have been approved by
the Employer. The Engineer already issued a letter to respond to the Contractor but the
completed documents of VO.04 which is the largest value has not been done to submit to the
Engineer for checking.
7. Re EX2- Record Photographs
Monthly Progress Report No.48, February 2014
18
Package EX2
Hanoi- HaiPhong Expressway Project
Concreting the pier column P2-B36
Concreting the bridge deck slab B37
Filling the bearing stone with
mortar B35
Launching the span 3 left Bridge B35
Concreting I33 girder Bridge B35
Tensioning I33 girder Bridge B35
Monthly Progress Report No.48, February 2014
19
Package EX2
Hanoi- HaiPhong Expressway Project
Preparing to install formwork at crossing beams B35
Installation of formwork and reinforcement steel A2
Abutment B19 Bridge
Casting the sample concrete of bored pile at A2 B35
Concreting I33 girder Bridge B35
Launching span 3 left Bridge B35
Base construction at Km11+060 – Km11+280
Monthly Progress Report No.48, February 2014
20
Package EX2
Hanoi- HaiPhong Expressway Project
Checking the slump of concrete cradle Km7+948.33
Wedge, anchorage test at ITST
Sampling the asphalt aggregate at the batching plant
Construction of drainage culvert at Km12+563
Granular backfilling at Km12+460
Construction of K95 embankment at Km12+320-Km12+440
Monthly Progress Report No.48, February 2014
21
Package EX2